Engineering Management (Solved Numerical Problems)
The following table gives the activities in a construction project and other relevant information: Indirect costs vary as follows: (a) Draw an arrow diagram for the project. (b) Determine the project duration which will result in minimum total project cost. (AMIE Summer 2021, 15 marks) The network for normal activity times indicates a project duration of 13 months with critical path: A – D – G (1 – 2 – 4 – 5) as shown in following figure. The crash cost slope for various critical activities of the project is given in following table. Among the critical activities A, D and G, the least expensive activity is A. This means that the duration of this activity should be crashed by maximum of one month. Thus, project duration reduces to 12 months and new total project cost is as follows: Total crashed cost = Total direct cost + Indirect cost due to crashing of activity A by one week + Indirect cost for 12 months = 713 + 1 × 30 + 250 = ₹ 993 Since existing critical path remains same even ...